r7 - 25 Jan 2006 - 12:10:05 - KatieCappsParlanteYou are here: OSAF >  Journal Web  >  StatusReports > ComprehensiveWeeklyStatusReports > WeeklyStatus20060124
This report covers the period from Jan 4 2006 to Jan 24 2006 (three weeks).

Highlights

  • Progress: Sprint week last week was great fun and useful.
  • Plans: Chandler 0.7 design is rolling into gear.

Design and PM (Sheila)

  • Progress:
    • Chandler
      • Specs in progress: markup bar, context menus, scheduling, timezones
      • Design discussions: scheduling (thurs), dashboard (mon), markup bar (next week)
    • Scooby
      • 0.1 planning page and feature list updated - design mockups in progress
    • Cosmo
      • reviewed 0.3 plan with BCM - discussed design requirements
  • Plans:
      • Finalize a number of discussions on the design list - emails about process, dogfooding
      • Specs due for next week - markup bar, context menus, scheduling
      • Continue developer discussions on the dashboard
      • Triaging dogfood feedback
      • Design feedback for Cosmo 0.3 screens

Application WG (Philippe)

  • Progress :
    • Sprints were great though not long enough to reach success for everyone (working parcels)
  • Plan :
    • Make progress on 0.7 Architecture tasks (see details in the meeting's minutes)
    • Review 0.7 bugs and prioritize
    • Create a Wiki page for "Geek Talk: subjects for Apps meeting (Philippe)

Platform WG (Katie)

  • Progress:
    • Progress on eggs, including build support (setuptools) and i18n support.
    • Parcel sprinting yielded parcels that queried eventful for events, and integration with Quicksilver and the OSX Dashboard (building on a XML-RPC connector).
    • Test sprinting yielded some WebDAV tests and some functional tests.
    • High level plan for who is working on what for 0.7 (see notes).
  • Plans:
    • Continue work on eggs
    • 0.7 i18n plan
    • 0.7 sharing spec
    • 0.7 recurrence and email specs (technical design for tenet features)
    • 0.7 domain model plan

QA, Build and Release (Heikki/Aparna)

  • Progress:
    • scooby test automation plan
    • Additional chandler functional tests from the sprints
  • Plans:
    • Functional tests on Tinderbox
    • scooby test plan

Cosmo and Scooby (Lisa/Bobby)

  • Progress: Cosmo 0.3 feature tasks split up between BKirsch and BCM. Scooby 0.1 release (pre-usable but may be interesting to volunteers) scoped for mid-February.
  • Plans: Cosmo feature development; Scooby finishing, move towards code complete, and help QA ramp up.

IT (Jared)

  • Progress:
  • Plans:

Community (Pieter/Ted)

  • Progress:
    • Open discussion on community topics during sprint week.
    • Lots of individual conversations about community with Cosmo and Scooby teams.
    • Initial drafts of governance principles.
  • Plans:
    • IRC discussion with Scooby team on community topics.
    • Schedule workshop for "information architect" position for early next week.
    • Keep working on governance drafts.
    • Come up with list of projects for OSU students
    • Start documenting committer policy
Edit | WYSIWYG | Attach | Printable | Raw View | Backlinks: Web, All Webs | History: r7 < r6 < r5 < r4 < r3 | More topic actions
 
Open Source Applications Foundation
Except where otherwise noted, this site and its content are licensed by OSAF under an Creative Commons License, Attribution Only 3.0.
See list of page contributors for attributions.