Agenda:

  • From last week: confirmation that we are in agreement with the release dates:
    • Code Freeze: February 21st 2006 (which basically means whatever that didn't make it in this release will be implemented in the next mile stone)
    • Ready to package with Cosmo: February 24th 2006
    • Scooby released with Cosmo: March (first week?)
  • Progress report on Scooby
    • Is the high level view working or is going through the bug list easier to comprehend?
    • How do we look at the latest development?
  • Testing Issues
    • Do you have everything set up so you can begin testing? Any additional issues?
  • Any further community issues or questions?
  • Scooby landing/project page (just a quick update on what is going on.)

Next Action Items

  • Scooby 0.1 release is TBD with Cosmo release, but will be ready by February 24th 2006.
  • Progress will be better defined with 'yes' or 'no' to a feature being completed. View update on the high level Scooby Planning page.
  • Testing for Scooby is good. Just need to follow up with testing for Cosmo.
  • Scooby landing/project page will be sent to the Scooby list for futher discussion.
Edit | WYSIWYG | Attach | Printable | Raw View | Backlinks: Web, All Webs | History: r2 < r1 | More topic actions
 
Open Source Applications Foundation
Except where otherwise noted, this site and its content are licensed by OSAF under an Creative Commons License, Attribution Only 3.0.
See list of page contributors for attributions.