Scooby Meeting Notes - February 15th 2006
Agenda:
From last week: confirmation that we are in agreement with the release dates:
Code Freeze: February 21st 2006
(which basically means whatever that didn't make it in this release will be implemented in the next mile stone)
Ready to package with Cosmo: February 24th 2006
Scooby released with Cosmo: March (first week?)
Progress report on Scooby
Is the high level
view
working or is going through the bug list easier to comprehend?
How do we look at the latest development?
Testing Issues
Do you have everything set up so you can begin testing? Any additional issues?
Any further community issues or questions?
Scooby landing/project page (just a quick update on what is going on.)
Next Action Items
Scooby 0.1 release is TBD with Cosmo release, but will be ready by February 24th 2006.
Progress will be better defined with 'yes' or 'no' to a feature being completed. View update on the high level
Scooby Planning
page.
Testing for Scooby is good. Just need to follow up with testing for Cosmo.
Scooby landing/project page will be sent to the Scooby list for futher discussion.
E
dit
|
W
YSIWYG
|
A
ttach
|
P
rintable
|
R
aw View
|
Backlinks:
We
b
,
A
l
l Webs
|
H
istory
: r2
<
r1
|
M
ore topic actions
Log In
or
Register
chandlerproject.org
VISION
TOUR
Download Desktop
Get a Hub Account
Get Chandler Server
FAQ
Get Started
Blog
Mailing Lists
Chat on IRC
Report a Bug
Get Involved
OSAF Community
About OSAF
Journal Wiki Changes
Open Source Applications Foundation
Dansk
Deutsch
English
Español
Finnis
Français
Italiano
Nederlands
Polski
Português
Svenska
简体中文
繁體中文
Except where otherwise noted, this site and its content are licensed by OSAF under an
Creative Commons License, Attribution Only 3.0
.
See
list of page contributors
for attributions.