Cosmo release of 0.3 may happen sometime in the first week of March.
Note: I never said "first week of March" - I said "two weeks of development" but didn't attach start and end dates. The actual timing depends on how many other OMG-super-high-top-priority things pop up. -bcm
Testing is the concern if Cosmo releases the same time as Scooby.
Scooby/Cosmo integration testing
Estimates of 3 or 4 days of integration Scooby/Cosmo integration testing
Progress report on Scooby
Scooby will extend it's release date by one week, but will be packaged with the release of Cosmo together in the first week of March
The release of Scooby 0.1 depends on features in the release of Cosmo 0.3. It does not make much sense to release Scooby 0.1 before Cosmo 0.3. Future development of Scooby may not require new features from Cosmo therefore future develpment of Scooby doesn't need to be tied to any release of Cosmo.
During this time, Scooby team will begin to work on the next milestone.
Is there a decision on packaging 'Snarf'?
Also needs QA to test – minimal test
Needs documentation two downloads /integrated bundle
May need a better name besides Snarf to quickly identify the Scooby/Cosmo bundle