r13 - 23 Aug 2005 - 13:52:35 - BrianKirschYou are here: OSAF >  Journal Web  >  DevelopmentHome > DeveloperPlatformProject > DevMtg20050823

services, repository and dev platform meeting

agenda

  • set branch: bugzilla
  • office hours schedule:
    • i18n
    • profiling (and other performance related discussions)
    • qa

status

Katie

  • Progress
    • Conversations with Mimi and Sheila about content model, removed a few unused attributes.
    • Ongoing set integration
    • Ongoing 0.7/0.8 planning and framework futures discussions
  • Plan

Morgen

  • Progress
    • Vacation
    • Tried activating repo view merging for sharing in the branch, ran into problems, so backed off
    • Ran through extended acceptance tests on the branch:
      • #7 Import of OSAF.ics: Successful, yet took 5 minutes to complete!
      • #8 Export to .ics: Successful, just tried exporting a calendar with 4 events in it, and iCal was able to read that in.
      • #9 Sharing calendars between 2 chandlers: Publishing to WebDAV server works; Subscribing works, however the events don't appear in the Week view, only List view
      • #10 Interoperability with iCal: Successful
      • #11 Third party parcels: Successful
  • Plan
    • Continue new collection itegration
    • Debug repo view merging

Brian K

  • Progress
    • Continued work on I18nmanager and LocalizableString?
    • Migrated Chandler code base to leverage OSAFMessageFactory?
    • Updated Chandler i18n wiki with 1.0 roadmap
    • Simplifed translation model and removed LocalizableString? dependency
    • Updated Chandler code base to use new translation mechanism without localizable string
    • Prepared for i18n office hours talk
    • Organized CPIA dialog code removing duplicate code definitions
    • Update locale setting code
  • Plan
    • Finish off i18n documentation updates
    • Create i18n busy developers guide
    • migrate displayName to use new Text type (formally UString)
    • Deprecate LocalizableString? and possible String as well
    • Rename BString Bytes
    • Migrate Chandler schema to leverage unicode Text type instead of String
    • Host i18n office hours
    • Run pygettext.py on Chandler code base and identify common reusable strings and move to central message file
    • Flying to SF on Friday Aug 26th will be online half day before going to airport

PJE

  • Progress
    • Drafted, discussed, posted API guidelines proposal
    • Ported Flickr parcel.xml to Python
    • Ported Amazon parcel.xml to Python
    • Ported osaf.framework.blocks' default styles to Python
    • Close out misc. bugs on bugzilla
    • Misc. developer assistance, API questions, Python questions, performance discussions, etc.
  • Plan
    • office hours on profiling?
    • studying repository performance
    • Finish parcel.xml conversions
    • Replace parcel loader
    • Make pim package conform to API guidelines (after sets merge lands)

Heikki

  • Progress
    • ACL: wrote classes that parse and understand the ACL features that a server supports
    • SSL: have proof of concept implementation for allowing users to ignore SSL errors
  • Plan
    • Organize a meeting with Mozilla people and our IT people to discuss webtools etc.
    • ACL: write function that maps a standard privilege to actual server privileges
    • SSL: checkin code that allows people some control to ignore SSL errors

Grant

  • Progress
    • timezone:
      • Bug:3767 (changing the timezone or start date of a recurring event blanks out parts of the detail view).
      • Bug:3784 (Change timezone pulldown font to match the font size in the detail view).
      • Bug:3801 ("Generate Data" shouldn't generate "floating" events)
      • In the works: Bug:3768, Bug:3783.
    • zanshin:
      • Started work on sending If-Match/If-None-Match headers.
      • Finished incorporating changes from review feedback.
      • Fixed a couple of bugs & added some unit tests.
  • Plan
    • More zanshin work (M5 tasks).
    • Fix timezone-related issues as they come up.

Jeffrey

  • Progress
    • Implemented proxy for the DV (still need to work a bit on the summary and calendar views)
    • Implemented recurrence change dialog
    • Discussed bug 3789, error when recurrence change deletes items, with Alec and Donn
    • Fixed bug:3785 (changing recurrence rules wasn't preserving end-of-recurrence date)
    • Fixed bug:3509 (exported All Day events were a day too short)
    • Started working on exporting recurring events
  • Plan
    • Get export of recurring events working at a basic level (just force timezones to US-Pacific for now)
    • Pack and move

Ted

  • Progress
    • set integration
    • FooCamp?
  • Plan
    • set integration
    • meetings with people in the office

Lisa

Edit | WYSIWYG | Attach | Printable | Raw View | Backlinks: Web, All Webs | History: r13 < r12 < r11 < r10 < r9 | More topic actions
 
Open Source Applications Foundation
Except where otherwise noted, this site and its content are licensed by OSAF under an Creative Commons License, Attribution Only 3.0.
See list of page contributors for attributions.